Education / Extra work and changes

In this lesson:

  • Separate the original job from a possible extra.
  • Compare a clear written instruction with a vague conversation.
  • Identify which messages show what each person accepted.

“I thought that was included.”
“No, mate. That was extra.”

Does this sound familiar?

Before the argument gets any further, take step back. What did you actually agree, and how was it agreed?

A deal can be agreed over WhatsApp, by email, on the phone or face to face. You don’t always need something signed. What was said, written, texted and done can all matter.

The trouble starts if each person remembers a different deal.

For example replacing a kitchen tap.

“£90 labour to replace the tap. You supply the new one. Any changes to the pipework would be extra.”

The customer replied “ok go ahead.”

That will give you a much clearer record than a quick “Yeah, just sort it out” during a phone call, followed by an argument what the the deal actually was when the work is finished.

So check the details:

  • What exactly was being fitted, repaired or replaced?
  • Was it a fixed price, an estimate or an hourly rate, was VAT included?
  • Who was supplying what?
  • Were they discussed and agreed, did you discuss the possibility of extras?
  • What exactly did the other person actually accept?

If you agree something verbally, send a short message afterwards confirming it. Don’t assume silence means acceptance, get a confirmation.

Is it already in a dispute?

Keep the full conversation, including the messages before and after the part you think proves your point.

And be honest about any weaknesses you have in your proof.

Whether you’re chasing payment or questioning the bill, start with the agreement. A few clear lines laying out exactly what is included before the job can save a lot of grief afterwards.

General information for England and Wales.

Put this lesson into practice

Using the kitchen-tap example below, write a short confirmation of the work, price, materials and excluded pipework. Then list what would need discussing if additional work became necessary.

Continue learning

Return to Education · Browse all lessons and articles

General education for England and Wales. These materials do not assess an individual case. Published by Tradesmen Dispute Direct.