Building and Repair Disputes: The Law Explained
By Tradesmen Dispute Direct · Updated 3 November 2026 · General information for England and Wales
Understand the law behind unpaid invoices, extra work and disputed repairs. Each topic explains the rule, shows how it works and identifies useful evidence. You do not need legal training. This guide covers England and Wales.
More topics: Consumer rights · Agency and authority · Contractors and subcontractors · Late payment · Negligence · Building safety · Case law
Court notices: Directions Questionnaire · Mediation · Court directions · Quick questions
The Court System
What Is the Small Claims Court in England and Wales?
The County Court deals with most everyday disputes about unpaid invoices and faulty building work. People often call part of this process the small claims court. There is no separate court with that name.
The claimant starts the court claim. The defendant answers it. A civil case concerns money or legal rights. It is different from a criminal prosecution.
If the claim is disputed, the court chooses a track. This means the set of rules used to manage the case. The small claims track is usually the simplest route for a straightforward money dispute.

How the Courts Fit Together
Start with the County Court and small claims explanations below. The other courts deal with larger or specialist cases and some appeals. An appeal asks a court to review an earlier decision. Your case does not automatically pass through every court.
WHERE MOST TRADES CLAIMS BEGIN
County Court
An electrician may ask the County Court to order payment of an unpaid £2,500 bill. A homeowner may ask it to award £3,000 for faulty repairs. In either case, the person making the claim must explain the agreement or legal duty, what went wrong and how the amount was calculated.
Small Claims Track
The small claims track is a simpler court process for many straightforward claims worth £10,000 or less. The limit is different for some injury and housing claims. The court also considers the type and complexity of the case.
You can usually present your own case without a solicitor. The hearing is less formal than a larger trial, but you must still follow court instructions and deadlines.
Court fees may be payable. There are limits on the legal costs the losing side can be ordered to pay, but small claims are not always free of costs.
OTHER CIVIL COURTS — SELECT A COURT FOR MORE DETAIL
Small Claims Court: Common Questions for Tradespeople
Can a tradesperson claim an unpaid bill? Yes, where there is a legal right to payment. Identify the customer who agreed to pay, explain why payment is due and show the calculation.
Can a homeowner claim for faulty work? Yes, where the work breaks the agreement or a legal duty and the remedy claimed is available. A remedy is the result the law allows, such as compensation or correcting the work.
Do I need a solicitor? You can usually represent yourself. Read the court papers carefully. Winning a judgment—the court’s decision—does not mean the court will automatically collect the money.
CONTRACT LAW PRINCIPLES
Contract Law for Builders and Tradespeople
Contract law explains when an agreement must be kept and what can happen if someone breaks it. For a building or repair job, the main questions are: what work was agreed, what was the price, who must pay, and did each side keep their promises?
You do not always need a signed document. Emails, messages, spoken agreements and what people actually did can help show what was agreed. These topics explain extra work, unpaid bills, defects, deductions and compensation.
See also Consumer Rights, Agency & Authority, fictional trades examples and real court decisions about contracts.
CONTRACT PRINCIPLE 01
Can an unsigned agreement still be binding?
A contract is an agreement the law can enforce. Usually, one person offers clear terms and the other accepts them. They intend to make a serious agreement, and each gives something in return: for example, building work in exchange for payment.
Acceptance can be written, spoken or shown by actions. You can have a contract even if nobody signed. The court looks at the whole exchange, including what happened before work started. If both sides made signing essential before any agreement could exist, that can change the answer.
Fictional example: A customer offers £5,000 for a clearly described wall. The builder reads the offer and starts that work without asking for a different price. Starting may show acceptance of the offer. The missing signature is not, by itself, a reason to double the price later.
Keep: the offer, replies, agreed description of the work and any statement about signing.
Read RTS Flexible Systems v Müller and the unsigned-quotation example.
CONTRACT PRINCIPLE 02
Who is the customer, and who owes the invoice?
The contracting parties are the people or businesses that made the agreement. Start with those names when deciding who can claim payment and who owes it. The property owner is not always the customer who made the contract.
An agent acts for someone else, called the principal. The agent needs authority: legal permission to make that agreement. Also, a limited company is separate from its directors. A director does not normally owe the company’s bill personally just because they ordered the work.
Fictional example: A landlord tells a plumber that a named manager can order repairs on the landlord’s behalf. The manager orders a £900 repair within that permission. This supports treating the landlord as the customer. If the management company instead agrees to buy the work in its own name, the contracting customer may be the company.
Keep: the order, accepted quotation and messages identifying who agreed to pay.
CONTRACT PRINCIPLE 03
What did the builder’s quotation or contract include?
A contract term is a rule or promise in the agreement. Terms can cover the price, materials, access, deadlines and the exact work included. That last point is often called the scope of work.
A fixed-price quote usually gives a price for stated work. An estimate usually gives an approximate cost. Read the actual wording: the label alone does not settle the question. Some terms are supplied by law even if the paperwork says nothing about them.
New terms on a later invoice do not automatically change an earlier agreement. The other side normally needs a proper chance to know the terms before or when agreeing.
Fictional example: An electrician quotes £850 to replace a consumer unit and says kitchen rewiring is excluded. The customer accepts. Those words support treating kitchen rewiring as extra work. If the quote promised both jobs, the same £850 could cover both.
Keep: the version of the quote and terms the customer actually accepted.
CONTRACT PRINCIPLE 04
Does consumer law apply to home repair contracts?
A consumer is an individual buying mainly for private use. A person having their own home repaired is usually a consumer. A company is not a consumer. An individual landlord ordering work for a rental business may also be acting for business purposes.
The Consumer Rights Act 2015 adds rights to consumer contracts. The trader must use reasonable care and skill: broadly, the standard expected of a competent person doing that trade. If no price or completion time has been agreed, the Act can supply rules about a reasonable price or time.
Fictional example: A homeowner’s shower leaks because the installer used unsuitable waterproofing. The homeowner can rely on the required standard of workmanship even if the quote did not mention a guarantee. The cause and quality of the work still need evidence.
Read Consumer Rights When Hiring a Tradesperson and section 49 of the Consumer Rights Act.
CONTRACT PRINCIPLE 05
Who must pay for agreed extra work?
A variation is an agreed change to the original job. It might add a radiator, remove an item or change the materials. First establish what the original price covered. Then identify the change, who approved it and the agreed extra charge or saving.
Some contracts require changes to be written and signed. These requirements can be legally effective, so a spoken instruction may not be enough. If extra work was requested but no price was agreed, a reasonable payment may sometimes be due. That is not permission to choose any price afterwards.
Fictional example: A builder offers to add underfloor heating for £600. The customer replies, ‘Yes, add it for £600.’ If this follows the contract’s rules for changes, the exchange supports the extra charge. A message saying only ‘go ahead’ is less useful without the earlier message showing what it approved.
Keep: the original scope, the full message exchange and any required written approval.
CONTRACT PRINCIPLE 06
What happens if someone breaks the agreement?
A breach of contract means failing to keep a legal promise in the agreement. Examples include not paying an amount due, using the wrong materials or refusing agreed access. Identify the promise and explain exactly how it was broken.
Termination means ending the contract. Suspension means stopping work temporarily. Neither is an automatic right after every problem. The contract or the law must give a proper basis for the step taken. Notice requirements may also apply.
Fictional example: A customer refuses the access needed to finish a kitchen. Messages recording the agreed visits and refusals may explain why the builder missed the date. But the builder should not assume that this allows them to abandon every remaining obligation. A small disagreement and a serious refusal to cooperate can have different consequences.
See Contractors & Subcontractors for special construction-payment and suspension rules.
CONTRACT PRINCIPLE 07
Can a customer hold back payment for faulty work?
Defective work falls below the agreed or legally required standard. A snag is usually a small item needing correction, such as unfinished paintwork. A serious defect may make the work unsafe or unusable.
A defect does not automatically cancel the whole bill. The important questions include how serious it is, what must be corrected and what a reasonable correction would cost. Consumer rights may also require the trader to put the service right or reduce the price, subject to the relevant conditions.
Fictional example: A customer holds back a £4,000 decorating balance because one skirting board needs repainting. Evidence of a small repair cost would not, by itself, explain a £4,000 deduction. A heating system that cannot heat the house and leaks fumes raises a much more serious failure.
Keep: the specification, clear defect photographs, repair quotations explaining the work needed, and offers to inspect or correct it.
Compare Hoenig v Isaacs and Bolton v Mahadeva, and read about consumer remedies.
CONTRACT PRINCIPLE 08
When is payment due, and can a deduction be made?
Check when the agreement says payment is due. It might be after a stage is finished, after approval by a named person or a set number of days after an invoice.
A retention is money the contract allows someone to hold back until a stated condition is met. For example, part may be held until the end of a period for reporting defects. A customer cannot simply invent a retention because they would prefer to pay later.
Set-off means using a legally valid claim against the other side to reduce money otherwise owed to them. A deduction must have a proper basis. Special construction-payment rules can also require notices before an amount may be withheld.
Fictional example: An invoice is £2,500 and the payer has a valid £200 deduction. If the contract and any required notices allow that deduction, the balance is £2,300. Alleging a £200 problem does not automatically remove the whole £2,500 debt. Missed notices can also affect what must be paid now.
CONTRACT PRINCIPLE 09
What losses can you claim if the agreement is broken?
Damages are compensation for a proven legal wrong. In a contract claim, the usual aim is to put the injured person financially where they would have been if the agreement had been kept. The aim is generally to compensate, rather than punish.
Explain how the broken promise caused each claimed loss. The loss must also be of a kind the law treats as within the parties’ reasonable expectations when they made the agreement. Unusual losses may depend on what the other side knew then.
You should take reasonable steps to avoid unnecessary extra loss. This is called mitigation. A claim for repairs should also explain any improvement beyond restoring what was lost, sometimes called betterment.
Fictional example: A faulty pipe connection floods a kitchen. Photographs, repair reports and invoices may support the cost of restoring it. The homeowner should take reasonable steps to limit further damage. Replacing serviceable parts of the kitchen with a more expensive design is not automatically a recoverable repair cost.
CONTRACT PRINCIPLE 10
Can contract terms remove or limit responsibility?
An exclusion clause says a business will not be responsible for a particular problem. A limitation clause sets a maximum amount it might have to pay. These terms must form part of the agreement, and the law can prevent them from working.
A trader cannot simply remove a consumer’s right to work done with reasonable care and skill. Certain terms between businesses must also pass a legal test of reasonableness. Under the Unfair Contract Terms Act 1977, responsibility for death or personal injury caused by negligence cannot be excluded.
Fictional example: A builder adds ‘no responsibility for defective work’ to the final invoice. That does not automatically remove responsibility. The customer may never have agreed to the term, and consumer law may prevent it operating anyway.
A separate issue is misrepresentation: an untrue statement of fact that leads someone to make a contract. For example, falsely claiming a qualification may create a claim if the customer relied on it and the legal requirements are met.
Read Consumer Rights Act, section 57, and the Unfair Contract Terms Act reasonableness test.
HOMEOWNERS AND CONSUMER LAW
Consumer Rights When Hiring a Tradesperson
Consumer law gives a private customer rights about workmanship, prices, promises, cancellation and faulty goods. These rights can apply even when the quotation does not mention them.
Start by checking who bought the work and why. Then use the topics below to understand the particular problem. A right to cancel after changing your mind is different from a right to complain about defective work.
CONSUMER LAW 01
Is the customer a consumer or a business?
A consumer is an individual buying mainly for private purposes. A trader supplies the work as part of a trade or business.
The customer’s purpose matters more than the building’s appearance. Work in a house is not always a consumer job. An individual landlord ordering repairs for a rental business may be acting in a business capacity. A limited company cannot be a consumer under these rules.
FICTIONAL TRADES EXAMPLE
Fictional example: Alex hires a decorator for the house where Alex lives. This is normally a consumer service. A property company hires the same decorator to prepare a rental house. The company is a business customer, even though the work looks identical.
Why it matters: identify the actual customer and purpose before applying consumer cancellation or service-remedy rules.
CONSUMER LAW 02
Cancelling a contract made at home or at a distance
Some consumer service contracts have a 14-day cooling-off period. This usually applies to contracts agreed away from the trader’s premises, such as at the customer’s home. It can also apply to contracts made entirely through an organised distance-sales system, such as online. Not every telephone call or home visit creates the same rights.
The trader must also explain that a customer who requests an early start may have to pay for the part supplied if they then cancel.
For a service contract, the normal period ends 14 days after the day the contract was made. The trader must give the required information about cancellation. Missing that information can extend the period, potentially by 12 months beyond its normal end.
Starting early does not automatically remove the right to cancel. The customer must expressly request an early start. For a contract made away from the trader’s premises, keep that request in a lasting form, such as an email.
If the customer cancels before completion, payment may be due for the part of the service already supplied. This is called proportionate payment. Missing the required information or early-start request can prevent charging for services supplied during the cancellation period. The right can end after full completion, but the customer must have requested the early start. Before work began, they must also have acknowledged that full completion would end the right.
There are exceptions. For example, a visit specifically requested for urgent repairs can be exempt for that urgent work. Additional non-urgent work can still have cancellation rights.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner agrees at home to pay £1,200 for decorating labour. The homeowner supplies the paint. The decorator gives the required information about cancellation and payment for an early start, and the homeowner emails a request to start immediately. The homeowner cancels six days later, before completion.
Why it matters: assuming the normal cancellation rules apply, the early start alone does not remove the right to cancel. The decorator may claim a proportionate amount for the service already supplied under the rules. That is different from automatically charging all £1,200. Without the required information or early-start request, entitlement to that payment can change.
CONSUMER LAW 03
The standard of work the law expects
A trader must do a consumer’s work with reasonable care and skill. This means the standard reasonably expected of a competent person doing that kind of job. Section 49 of the Consumer Rights Act 2015 puts this requirement into the contract.
The customer does not need to show deliberate wrongdoing. But being unhappy with the result does not, by itself, prove poor workmanship. Identify the actual defect and the evidence that the work fell below the required standard.
FICTIONAL TRADES EXAMPLE
Fictional example: A shower leaks. Inspection evidence shows the installer used waterproofing unsuitable for that shower. This can support a claim that the installer failed to use reasonable care and skill. If the leak instead came from an unrelated pipe damaged later, the same complaint would need a different explanation.
Keep: the product details, photographs and evidence of the leak’s cause.
CONSUMER LAW 04
What was promised about the work and materials?
What a trader says about a service can become part of a consumer contract. Under section 50, the customer’s decision matters: did they take that information into account when choosing the service or making a later decision about it?
A promise about a named product, standard or service is not automatically lost because the final paperwork is short. Any qualifications to the promise and any change expressly agreed later also matter. Keep advertisements, quotations and messages showing what was promised.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner chooses a roofer partly because the quote promises a named waterproof membrane. The roofer installs another brand without agreement.
Why it matters: the issue is whether the promised product became part of the contract. The roofer cannot settle that question simply by saying the substitute was just as good. A later express agreement to the substitution could change the answer.
CONSUMER LAW 05
Price, timing and completion
If a consumer contract has no agreed price, or method for working it out, section 51 normally requires a reasonable price. If no completion time is fixed, section 52 requires completion within a reasonable time.
These are fallback rules. They do not let someone replace a price or date that was already agreed. What is reasonable depends on the work and circumstances, such as its size, normal costs and any genuine urgency.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner asks a plumber to stop a leak without agreeing a price. The plumber must be able to explain a reasonable charge for the authorised work. Hours, materials and comparable charges may help. An invoice alone does not show that any amount chosen is reasonable.
If the plumber had instead quoted £500 and the customer accepted, that agreement would normally be the starting point. Properly agreed extras could still change the total.
CONSUMER LAW 06
Putting faulty work right or reducing the price
Where a consumer service fails the required standard, the customer may require the trader to correct it. The law calls this repeat performance. It means doing what is needed to bring the service into line with the contract, rather than automatically repeating every part of the job.
The trader must pay the necessary correction costs. The correction must be completed within a reasonable time and without significant inconvenience to the customer.
If correction is impossible, or the trader fails those requirements after being asked, an appropriate price reduction can become available. This reduces the bill or refunds an appropriate amount already paid. In some cases the reduction can reach the whole price.
These rules are in sections 54–56 of the Consumer Rights Act. Other remedies, including compensation, can also apply. Different routes can apply to delay or certain broken information promises. There is no universal rule that every complaint requires another attempt or a full refund.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner pays for a level tiled floor, but poor installation leaves the tiles uneven. The homeowner asks the tiler to correct it. If the work failed the required standard, the necessary correction should not bring a second labour or materials bill.
If correction is impossible, or the tiler fails to correct it within a reasonable time and without significant inconvenience, the price-reduction route becomes relevant. The amount should reflect the circumstances; uneven tiles do not automatically mean every pound paid must be refunded.
CONSUMER LAW 07
Unfair terms, deposits and cancellation fees
A consumer term can be unfair if it gives the trader a significant unfair advantage at the customer’s expense and is contrary to fair and open dealing. An unfair term is not binding on the consumer.
Examples that may need checking include excessive cancellation charges, an unrestricted power to change a fixed price or an attempt to remove legal service rights. The words ‘non-refundable deposit’ do not, by themselves, settle whether the trader can keep the money.
However, a customer who changes their mind does not always have a right to a full refund. First distinguish a legal cooling-off cancellation from cancellation outside that right. Then check the agreement, the applicable law and the basis for any charge.
FICTIONAL TRADES EXAMPLE
Fictional example: Outside any cooling-off right, a customer cancels a decorating booking. The decorator saves the materials and labour costs and fills the same slot with another job. A term still demands the full original price.
Why it matters: a charge far beyond the trader’s justified loss may be unfair. The trader should explain the basis of the charge. The customer should not assume that every cancellation automatically means the deposit must be returned in full.
CONSUMER LAW 08
Goods, installation and guarantees
A fitted boiler or window involves a product as well as work. Consumer law sets standards for goods, including satisfactory quality and, where applicable, suitability for a purpose made known to the trader.
If the supply contract includes installation by the supplier or under its responsibility, incorrect installation can also mean the goods fail to meet that contract. If one business sells the product and another is separately hired to fit it, identify what each agreed to provide.
A manufacturer’s warranty can give extra protection. It does not automatically replace legal rights against the business that supplied the goods. Remedies for faulty goods have their own rules, so do not assume every product complaint follows the same steps as a workmanship-only complaint.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner buys a boiler from one heating company under a supply-and-install contract. The company fits it incorrectly. The customer can raise that installation problem with the supplying company; it is not automatically just a manufacturer’s-warranty issue.
If the homeowner bought the boiler from a retailer and separately hired an installer, a product fault and poor fitting may involve different businesses. Keep both contracts and evidence showing which problem caused the loss.
Read the law: Consumer Rights Act 2015: services and Consumer Contracts Regulations 2013: information and cancellation.
The real court decisions about statutory rights and fair terms explain related issues. Many consumer rights come directly from legislation: rules made by Parliament, rather than one particular court case.
CONTRACTORS & SUBCONTRACTORS
Who Pays Whom — and Who Is Responsible for the Work?
A customer may hire a builder, who then hires a plumber or another trade. The builder is the main contractor. The trade hired by the builder is a subcontractor. Start by identifying who agreed to do what, and who agreed to pay. Different rules may apply to payment, tax and site safety.
SUBCONTRACTOR RULE 01
Separate agreements: customer, builder and subcontractor
There are often two separate contracts: the customer’s agreement with the builder, and the builder’s agreement with the subcontractor. Each can have its own price, work description and payment dates.
The subcontractor normally asks the builder for payment. The homeowner does not automatically owe that bill just because the work improved their home. Similarly, the homeowner cannot automatically enforce the builder’s subcontract.
A different result needs a legal reason. For example, the homeowner might separately promise to pay, or a contract might give them a right to enforce a particular promise. A collateral warranty is a separate promise made to another person, such as the building’s owner or tenant. An assignment is a legal transfer of a right to someone else. The wording and legal requirements must be checked.
A claim for careless work that damages property may raise separate negligence rules. It does not make the two contracts into one.
FICTIONAL TRADES EXAMPLE
Fictional example: A building company hires a roofer for £3,000. The homeowner has no separate agreement with the roofer. The roofer’s payment claim is normally against the building company. The homeowner paying the builder late does not, by itself, turn the homeowner into the roofer’s customer.
SUBCONTRACTOR RULE 02
Who is responsible for a subcontractor’s faulty work?
A builder does not usually escape a promise to the customer by hiring someone else to do the work. If the builder promised a properly tiled bathroom, using a subcontractor does not remove that promise.
The customer may have a contract claim against the builder. The builder may then have a separate claim against the tiler under their subcontract. Each claim needs evidence of what was promised, what went wrong and the resulting loss.
Where the dispute concerns damage caused on site, identify what each person actually did. Being present at the property is not proof that someone caused the damage.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner pays a builder to supply and fit a bathroom. The builder hires a tiler, whose work is defective. The homeowner can raise the broken promise with the builder. The builder cannot answer simply, “The tiler is self-employed.” Any claim the builder has against the tiler is a separate matter.
SUBCONTRACTOR RULE 03
The work, extra charges and money held back
A subcontract should say what work is included, the price or hourly rate, the dates and who can approve extra work. It should also explain how payment is requested and when it is due.
A variation is an agreed change to the original job. Before doing extra work, record what is changing, its price and who has authority to agree it. Check any rule requiring written approval. A site manager asking for a change does not always have authority to promise extra payment.
Retention is an agreed amount held back until a stated condition is met. For example, the contract might allow 5% to be held until specified finishing defects are corrected. The customer cannot invent a retention after the event.
An unsigned subcontract can still matter if the parties agreed its terms through messages or their actions. Keep the proposed terms and the messages showing what was accepted.
FICTIONAL TRADES EXAMPLE
Fictional example: A plumber’s £1,800 price covers fitting hidden pipes before the walls are closed. Fitting taps afterwards is outside that agreed work. The builder’s authorised manager approves an extra £400 by email. That email helps show a separate price was agreed. Without it, the plumber would need other evidence that the extra work and payment were authorised.
SUBCONTRACTOR RULE 04
When do special construction-payment rules apply?
The Housing Grants, Construction and Regeneration Act 1996, often called the Construction Act, gives special rights under certain construction contracts. Many building, repair, alteration and maintenance jobs can fall within it. Some activities and contracts are excluded.
For a contract covered by the Act, there must be rules for calculating payment and deciding when it is due. Formal payment notices can affect what must be paid now. The Act also provides a way to ask an independent specialist to decide a dispute, called adjudication.
A missing signature does not automatically prevent these rules applying. An agreement made by email or spoken words can be covered. Check the type of work, the people who made the contract and the exclusions before relying on the Act.
FICTIONAL TRADES EXAMPLE
Fictional example: Two businesses agree a building subcontract by email and the subcontractor starts work. The main contractor later says payment-notice rules cannot apply because no paper contract was signed. That is not enough: an unsigned agreement can still be covered by the Construction Act.
SUBCONTRACTOR RULE 05
Homeowner contracts: when payment rules differ
The Construction Act’s payment and adjudication rules do not cover every job. One important exclusion concerns a contract mainly for work on a house or flat which one of the contracting parties lives in, or intends to live in, as their home. This is called the residential-occupier exclusion.
Look at each contract separately. The homeowner’s contract with a builder may be excluded. The builder’s subcontract with a plumber on that same house may still be covered. A landlord arranging work on a tenant’s home is not automatically treated like an owner arranging work on their own home.
This is a different question from whether someone is a consumer under consumer law. Also check whether the parties agreed a dispute process in their contract, even if the Act does not provide one.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner hires a builder to renovate the house they live in. The builder hires a plumber for £3,000. The homeowner–builder contract may fall within the residential-occupier exclusion. That does not automatically exclude the separate builder–plumber contract. The address is the same; the contracting parties are different.
SUBCONTRACTOR RULE 06
Requests for payment and notices reducing payment
For a construction contract covered by these rules, distinguish the due date, when a payment becomes due, from the final date for payment, the deadline for paying it.
A payment notice states the amount considered due and how it was calculated. Depending on the contract, the person paying or the person being paid gives it. If a required notice is missing, the law can allow a replacement notice or treat an earlier valid payment application as the notice.
The amount established under these notice rules is the notified sum. To pay less, the payer usually needs a valid pay less notice. It must state the amount considered due and its calculation, and arrive within the required time.
The contract and the legal rules control the dates and method. A general complaint about workmanship is not necessarily a valid notice. A duty to pay the notified sum now can exist even while the final value of the work remains disputed.
FICTIONAL TRADES EXAMPLE
Fictional example: Under a covered subcontract, the notice rules establish £5,000 as the notified sum. The builder believes £1,000 should be deducted but misses the deadline for a valid pay less notice. Subject to any applicable exception, £5,000 may have to be paid now. That does not finally decide whether the work was worth £5,000; a later assessment can address that question.
SUBCONTRACTOR RULE 07
Quick dispute decisions, stopping work and delayed payment
Adjudication is a construction-dispute process in which an independent adjudicator gives a decision. For contracts covered by the Act, a party can normally refer a dispute at any time. The decision is usually binding for the time being. A court, arbitration or later agreement can finally resolve the dispute. Adjudication is different from a County Court small claim.
The Act can also allow work to be suspended for specified non-payment. The legal conditions must be met, including giving at least seven days’ notice stating the grounds. An overdue invoice alone is not permission to walk off site immediately.
A pay-when-paid clause says the contractor will pay a subcontractor only after receiving money from someone else. Such a clause is generally ineffective under a covered contract. There is a specific exception involving insolvency, so check the contract and the facts.
FICTIONAL TRADES EXAMPLE
Fictional example: A builder owes a plumber £3,000 under a covered subcontract. The homeowner has not paid the builder, but nobody in the payment chain is insolvent. A clause saying “we pay you when the homeowner pays us” does not normally excuse non-payment. The builder’s customer debt and its debt to the plumber are separate.
SUBCONTRACTOR RULE 08
Tax taken from subcontract payments (CIS)
The Construction Industry Scheme (CIS) is a tax system for certain payments to construction subcontractors. A contractor checks the subcontractor’s status with HMRC. Where a deduction is required, the contractor takes the correct amount from the payment and pays it to HMRC.
The calculation excludes certain amounts, including eligible materials costs, under HMRC’s rules. The contractor must keep records, provide the required payment and deduction statement and report the payments.
A CIS deduction is a payment towards tax. It does not change the agreed price for the work or give the contractor a general right to withhold the whole bill. CIS registration also does not, by itself, prove someone is self-employed for employment rights.
FICTIONAL TRADES EXAMPLE
Fictional example: A labour-only subcontractor is owed £1,000, with no VAT or other excluded costs in this example. HMRC says the deduction rate is 20%. The contractor pays £800 to the subcontractor and accounts for £200 to HMRC. The £200 must be shown as a tax deduction; it is not a discount on the agreed price or money the contractor can simply keep.
SUBCONTRACTOR RULE 09
Is a subcontractor really self-employed?
Calling a person “self-employed” in a contract does not settle their legal status. The real working arrangement matters. For example, who controls the work, whether the person must do it personally, and whether they are running their own business can be relevant.
Employee, worker and self-employed person are different legal categories. Employment rights and tax status must be considered under their own rules. Paying someone through CIS does not answer every employment question.
Site safety is another separate issue. Under the Construction (Design and Management) Regulations 2015, a principal contractor manages construction health and safety on projects needing that role. The title does not, by itself, identify who owes a particular invoice.
FICTIONAL TRADES EXAMPLE
Fictional example: An installer works fixed hours, must do the job personally and follows a manager’s detailed instructions. The contract calls the installer self-employed. Those facts need to be assessed; the label alone does not decide employment rights. Separately, the payment agreement identifies who owes the installer money, and safety rules identify who manages the site.
Read the official sources: Construction Act 1996; contracts with residential occupiers; rights given to someone outside a contract; HMRC’s CIS guide; HSE’s contractor safety duties; and ACAS employment-status guidance.
This is general information for England and Wales. Payment notices, suspension and adjudication have detailed rules. Check them for your contract before acting. See construction contract cases and fictional trades examples.
LATE PAYMENTS, DEBTS AND BUSINESS RISK
Getting Paid: Interest, Deductions and Customers Who Cannot Pay
Start with who owes the money, how much is due and the payment date. Some business debts allow extra interest and a fixed recovery charge. Different rules apply when the customer is a consumer, when deductions are disputed, or when a company cannot pay its debts.
PAYMENT PRINCIPLE 01
When is a trades invoice actually due?
Check the agreed payment terms. Payment might be due on a fixed date, after a stage of work or after an agreed completion certificate. An invoice cannot usually change those terms just by printing an earlier deadline.
If no payment date was agreed, the law may supply rules. For business debts, check the late-payment rules. For construction contracts, check whether the special payment rules apply.
If completion is disputed, identify exactly what remains unfinished and why it matters to the payment condition. Keep the quotation, work order, completion records, invoice and payment history together.
FICTIONAL TRADES EXAMPLE
Fictional example: The final £2,000 is due when a building reaches “practical completion”. This usually concerns whether the work is sufficiently complete for its intended use, but the contract matters. A missing door handle and a missing staircase are very different problems. The words on the invoice alone do not decide whether the payment condition has been met.
PAYMENT PRINCIPLE 02
Why consumer debts are different
The commercial late-payment charges below normally concern debts owed by businesses or public bodies. They do not automatically apply when an individual buys a repair for their private home.
A homeowner’s debt can still be overdue and enforceable. Interest might be available under a valid contract term or a court’s legal power to award it. Explain the correct reason for claiming interest; do not copy business-debt charges onto every invoice.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner owes £450 for repairing their own kitchen sink. The plumber cannot automatically add the £40 commercial recovery charge just because payment is late. The plumber must use the rules that apply to this consumer debt.
PAYMENT PRINCIPLE 03
Interest on late business payments
For a business debt covered by the Late Payment of Commercial Debts (Interest) Act 1998, the usual statutory interest rate is eight percentage points above the relevant Bank of England base rate. “Statutory” means the right comes from legislation.
This is an annual rate. Work out interest for the number of days the payment was late. Do not add the whole annual percentage as a one-off fee. Use the reference rate that applies to the relevant period, rather than assuming today’s rate applies throughout.
An agreed contractual interest remedy can affect whether the statutory rules apply. Check the contract, when payment became overdue and the dates of any part-payments.
FICTIONAL TRADES EXAMPLE
Fictional example: A letting agency orders maintenance in its own company name and agrees that it will pay. Its business debt of £1,000 is paid 30 days late. If the applicable annual interest rate were 12%, the calculation would be £1,000 × 12% × 30 ÷ 365 = £9.86. This rate is only an illustration; check the actual rate and whether the statutory rules cover the debt.
PAYMENT PRINCIPLE 04
Fixed late-payment charges: £40, £70 or £100
For a late business debt covered by the commercial-payment rules, the supplier can claim a fixed amount towards recovery costs:
- £40 for a debt below £1,000.
- £70 for a debt from £1,000 to below £10,000.
- £100 for a debt of £10,000 or more.
The charge relates to a qualifying late payment. It is not a fresh charge for each reminder, and it does not automatically apply to a private homeowner. Interest is a separate calculation.
FICTIONAL TRADES EXAMPLE
Fictional example: A business separately orders two £600 jobs. Each creates a separate debt covered by the commercial late-payment rules, and both are paid late. The fixed amounts are £40 + £40 = £80. One covered debt of £1,200 instead attracts £70. Splitting one debt into extra invoices does not automatically create extra entitlements.
PAYMENT PRINCIPLE 05
Money held back and claims for deductions
A customer needs a legal or contractual basis for taking money off a bill. They should explain the defect or other claim, provide evidence and show the calculation.
Set-off means using a valid claim against the other party to reduce what is payable, where the law or contract allows. Retention means holding an agreed sum until a stated condition is met. A contract may also set an amount payable for specified delay, often called liquidated damages. The term still has to be legally valid. These are different reasons for a deduction; none should be assumed.
For a construction contract covered by payment-notice rules, a valid claim for defects does not remove the need to follow those rules. What must be paid now and the final amount owed can be different questions.
FICTIONAL TRADES EXAMPLE
Fictional example: A developer withholds an £8,000 subcontract payment, saying a defect will cost £300 to repair. The developer needs evidence for the deduction and must follow any applicable notice rules. A complaint about £300 does not, on its own, explain withholding all £8,000.
PAYMENT PRINCIPLE 06
Limited companies and personal guarantees
A limited company is legally separate from its directors and owners. If the company made the contract, it normally owes the bill. A director signing or ordering work for the company does not automatically promise to pay personally.
A personal guarantee is a separate promise by a person to pay if the company does not. Its wording and legal requirements matter. Other personal claims can exist, for example where a person’s own false statement creates a legal claim, but that needs a separate basis and evidence.
Check the company’s full registered name, number and the name on the agreement. A trading name is only a business label; it does not always identify the legal person who owes the money.
FICTIONAL TRADES EXAMPLE
Fictional example: The contract names Smith Developments Ltd and the director orders the work on its behalf. The company later closes its business. The director does not automatically owe the invoice personally. A valid personal guarantee could change that result; the director simply owning another successful business does not.
PAYMENT PRINCIPLE 07
What if the customer’s company cannot pay?
A company can be insolvent because it cannot pay its debts or because its debts exceed its assets. A formal process such as liquidation or administration may change how creditors can pursue payment.
In liquidation, a liquidator deals with the company’s affairs and available assets. In administration, an administrator manages the company under a legal rescue or recovery process. A creditor may need to send a proof of debt: a claim explaining the amount owed, with supporting documents.
Money is distributed under legal priority rules. A court judgment does not guarantee payment or automatically move an ordinary creditor to the front of the queue. Some court action or enforcement may be restricted.
A company removed from the register is dissolved. Restoring it to the register is a separate process. Check Companies House and insolvency notices before spending more on a claim.
FICTIONAL TRADES EXAMPLE
Fictional example: A subcontractor has a £7,000 judgment against a company that enters liquidation. The subcontractor should contact the liquidator about proving the debt. If little money is available after higher-priority claims, the subcontractor may receive only part of the £7,000 or nothing. Winning the case did not create money in the company.
PAYMENT PRINCIPLE 08
Settlements, payment plans and transferred debts
A full and final settlement is an agreement intended to end the identified dispute on stated terms. Write down the amount, payment dates and whether it covers the invoice, interest, fees and any counterclaim.
For an instalment plan, explain what happens if a payment is missed. Do not assume that any part-payment cancels the remaining debt, or that every offer to accept less has the same legal effect. Clear agreed wording matters.
A creditor can sometimes transfer the right to a debt to someone else. This is called assignment. The transfer, any required notice and any contract restrictions must be checked. A new name on a demand is not, by itself, proof of a valid transfer.
FICTIONAL TRADES EXAMPLE
Fictional example: A customer offers £3,000 to settle a disputed £5,000 bill. The parties should state whether £3,000 ends the whole dispute, or is only a payment towards it. If payment is by instalments, they should also agree what happens if an instalment is missed. Otherwise they may disagree later about whether the remaining £2,000 is still owed.
Official sources: interest on late business payments, fixed recovery charges and Companies House.
For the next steps, read Before Court and Running a Small Claim. For cases involving construction payments and insolvency, see Bresco and the other construction cases.
NEGLIGENCE PRINCIPLES
Negligence and Damage to Property
Negligence is a legal claim about a failure to take reasonable care which causes harm the law recognises. A poor result alone is not enough. This section explains the required duty, the careless act, the link to the damage and the loss claimed.
NEGLIGENCE PRINCIPLE 01
A broken agreement or a failure to take care?
A contract claim asks whether someone failed to do what their agreement required. A negligence claim asks whether they broke a legal duty to take reasonable care and caused harm for which the law allows compensation.
The same event can raise both questions, but a broken promise is not automatically negligence. The cost of correcting defective work itself is often dealt with through contract or consumer law.
Negligence is especially relevant where careless work injures someone or damages other property. It can also matter when the injured person never hired the contractor, such as a neighbour whose property is damaged.
FICTIONAL TRADES EXAMPLE
Fictional example: A plumber fits a faulty pipe. The customer may use their contract rights to seek the cost of correcting it. If the pipe leaks and damages the kitchen below, that additional damage may also support a negligence claim. The customer still needs to show what the plumber did wrong and how it caused the damage.
NEGLIGENCE PRINCIPLE 02
Did the contractor owe a duty to take care?
A duty of care is a legal responsibility to take reasonable care to avoid certain harm to another person. Tradespeople can owe duties to people affected by their work, including people who did not hire them.
The duty has limits. The court considers the relationship, the risk and the kind of loss claimed. It does not assume that everyone owes everyone else a duty to prevent every financial loss.
Start with a clear question: what harm should this person reasonably have taken care to avoid when doing this work?
FICTIONAL TRADES EXAMPLE
Fictional example: A scaffolder works beside a neighbour’s roof. The neighbour never hired the scaffolder. That does not remove the duty to take reasonable care not to damage the roof. The neighbour would still need evidence of careless work, resulting damage and the loss claimed.
NEGLIGENCE PRINCIPLE 03
What care should a competent tradesperson take?
The court asks what a reasonably competent person doing that type of work should have done. It considers the risks and the circumstances at the time. Relevant evidence can include trade practice, drawings, safety rules, manufacturer instructions and warnings.
A breach of duty means the person fell below that required standard of care. Something going wrong is not enough by itself. Equally, saying “I always do it this way” does not prove that the method was reasonable.
If a contractor claims specialist skills, that claim may be relevant to the standard expected.
FICTIONAL TRADES EXAMPLE
Fictional example: A manufacturer’s instructions require a particular protective fitting, but the electrician leaves it out. Those instructions help explain what a competent installer should have done. To claim compensation, the customer must also connect the failure to the loss being claimed.
NEGLIGENCE PRINCIPLE 04
Did the failure actually cause the damage?
Causation means the link between what someone did wrong and the damage claimed. The person bringing the claim normally has to show that link. Showing careless work and showing damage are not enough if the two are unrelated.
Ask whether earlier defects, later alterations, weather or another contractor’s work could explain the damage. The fact that a problem appeared after a visit does not, on its own, prove that visitor caused it.
Use dated photographs, job sheets, messages and a timeline. Where the cause is technical, a suitably qualified person’s evidence may be needed.
FICTIONAL TRADES EXAMPLE
Fictional example: A roof leaks after scaffolding is removed. Earlier photographs show a cracked tile in the same area. The owner needs evidence explaining whether the scaffold work caused new damage or the old crack caused the leak. The timing alone does not choose between those explanations.
NEGLIGENCE PRINCIPLE 05
Which losses can be claimed?
Negligence can provide compensation for injury and physical damage to property. Financial losses resulting from that harm may also be recoverable if the legal tests are met.
The rules are more restrictive where the loss is only financial. Lawyers call this pure economic loss. For example, the cost of replacing a defective item itself may be treated differently from the cost of repairing other property it damaged.
This does not mean the customer has no remedy for the defective item. Contract rights, consumer rights or a specific legal duty may provide one. Identify each loss and the legal reason for claiming it; avoid counting the same loss twice.
FICTIONAL TRADES EXAMPLE
Fictional example: A badly fitted valve needs £80 of corrective work and causes £4,000 of water damage to a ceiling and flooring. Keep the two amounts separate. The £80 may be claimed under the installation contract; the £4,000 may also raise negligence. The claimant must prove the cause and reasonable repair costs.
NEGLIGENCE PRINCIPLE 06
When more than one contractor may be responsible
More than one person can contribute to the same damage. The court may need to decide what each person did and whether each is legally responsible.
Being the last trade on site does not automatically make someone responsible for everything discovered afterwards. Separate each allegation and the evidence supporting it.
A person held liable can sometimes seek a contribution from another person responsible for the same damage. This means asking that person to pay an appropriate share. It is a separate legal issue from simply dividing the bill equally among everyone who attended.
FICTIONAL TRADES EXAMPLE
Fictional example: A plumber fits a pipe joint and a later contractor alters it. The joint then leaks. The investigation should identify its original condition, the later change and the cause of failure. The plumber is not automatically responsible because they first installed it, and the later contractor is not automatically responsible because they touched it last.
NEGLIGENCE PRINCIPLE 07
Did the customer help cause or increase the damage?
Contributory negligence concerns a person’s own unreasonable conduct helping to cause their injury or damage. Where the rule applies, compensation can be reduced to reflect their share of responsibility. It does not automatically defeat the whole claim.
Mitigation means taking reasonable steps to limit a loss. If someone could reasonably prevent extra damage but does not, they may be unable to recover that avoidable extra cost.
These questions can overlap, but they are different. One asks whether the claimant helped cause the harm. The other asks whether they reasonably limited the loss. A claimant does not have to take unsafe steps or accept any proposal the other side makes.
FICTIONAL TRADES EXAMPLE
Fictional example: A faulty fitting causes a leak. The customer is told how to stop further damage safely and has a reasonable opportunity to do so, but leaves the water running for days. The original fault may still support a claim. The avoidable extra damage is a separate issue and may reduce what can be recovered. If stopping the leak was unsafe or impractical, that could change the assessment.
NEGLIGENCE PRINCIPLE 08
What evidence is needed?
The person alleging negligence normally needs to establish four things:
- A duty to take reasonable care.
- A failure to meet that duty.
- A link between that failure and the damage.
- A loss for which the law allows compensation.
The usual civil standard is more likely than not, called the balance of probabilities. Match each disputed point to evidence: photographs, job records, messages, repair bills or witnesses with first-hand knowledge.
Technical disputes may need expert evidence. Court permission is required to use expert evidence at a small-claims hearing. A repair quotation is not automatically an independent expert report about the cause.
FICTIONAL TRADES EXAMPLE
Fictional example: A photograph shows a damaged ceiling. A dated job sheet records which pipe was repaired. A report explains how a faulty joint caused the leak, and an invoice records the reasonable repair cost. These documents answer different questions. The ceiling photograph alone does not establish all of them.
This is general educational information. TDD mainly supports eligible contract and payment disputes. Complex negligence claims may need specialist legal advice. See the fictional damage and safety examples and related court cases.
BUILDING, SAFETY & COMPLIANCE
Building Regulations and Safety Rules for Tradespeople
Agreeing a price and finishing the work are only part of a contractor’s responsibilities. Building, safety, environmental and property rules can also require permissions, certificates, qualifications or particular working methods. Breaking one of those rules and owing compensation to a customer are separate legal questions.
COMPLIANCE TOPIC 01
Building Regulations and planning permission
Planning permission concerns whether a proposed development is allowed, including matters such as its use, size and appearance. Building Regulations set standards for how work is designed and built, including structure, fire safety and energy use. Some jobs need both.
Building-control approval or notification may be needed for work such as extensions, roof changes, heating or electrical installations. Approval for planning purposes does not replace building-control requirements.
Before starting, identify which rules apply, who will arrange approval and what completion documents must be provided. England and Wales can have different requirements.
FICTIONAL TRADES EXAMPLE
Fictional example: A homeowner obtains planning permission for a loft conversion. Structural work also needs building-control approval. The builder cannot assume that the planning permission covers that separate requirement. The permission to develop and the checks on how it is built serve different purposes.
COMPLIANCE TOPIC 02
Who can certify work, and which records are needed?
A competent-person scheme lets a registered installer certify that specified work complies with Building Regulations. For work covered by the scheme, this can replace a separate building-control application. Registration must cover the actual type of work.
Electrical work can require testing, an installation certificate and, for certain jobs, notification under Building Regulations. These documents have different purposes. Part P is the part of the regulations dealing with electrical safety in homes; the notification rules differ between England and Wales.
Agree who will arrange the required notification, inspections and certificates. A promise to supply a certificate is not fulfilled merely because the equipment switches on.
FICTIONAL TRADES EXAMPLE
Fictional example: An electrician replaces a home’s consumer unit, the box containing circuit breakers. The homeowner should receive the documents required for that work. An electrical test certificate and a Building Regulations compliance certificate answer different questions, so asking only for “the certificate” may leave an important document missing.
COMPLIANCE TOPIC 03
Qualifications for gas and refrigerant work
For regulated gas work, use a Gas Safe registered business and an engineer qualified for that category of work. Registration for one type of appliance does not authorise every type of gas job. Check the engineer’s registration and the work categories on their card.
F-gases are gases used in some refrigeration, air-conditioning and heat-pump systems. Work on equipment containing them can require individual qualifications and, for businesses working on other people’s equipment, company certification. The exact requirement depends on the equipment and task.
Electrical work has its own competence and building-control rules. A general builder’s title does not replace any specialist requirement.
Gas-work registration requirements; individual F-gas qualifications; F-gas company certification.
FICTIONAL TRADES EXAMPLE
Fictional example: A builder includes a gas-boiler replacement in the job and uses someone who is not properly registered for the gas work. The boiler producing heat does not make that lawful. Any customer’s claim about the bill or the cost of putting matters right still needs its own contractual or other legal basis.
COMPLIANCE TOPIC 04
Who must plan and manage building-site safety?
The Construction (Design and Management) Regulations 2015, usually called CDM, set responsibilities for managing construction health and safety. They cover clients, designers and contractors.
For a private homeowner’s project, the client’s duties normally pass to the sole contractor. On a project with more than one contractor, they normally pass to the principal contractor, who manages construction safety. In some circumstances a principal designer can take on the client’s duties through a written agreement.
If the homeowner has not appointed a principal contractor, the contractor controlling construction takes on the relevant duties under the rules. This safety role does not automatically identify who owes each subcontractor’s invoice.
FICTIONAL TRADES EXAMPLE
Fictional example: A builder manages a home renovation involving a plumber and an electrician. The homeowner is not expected to organise construction safety simply because they own the house. The CDM roles need to be identified, and the contractor controlling the work may carry the relevant duties even if nobody used the title “principal contractor”.
COMPLIANCE TOPIC 05
Work at height, scaffolding and safe access
Work at height means work where a fall could cause injury. It can include ladders, roofs and work beside an opening; it is not limited to tall buildings.
The Work at Height Regulations 2005 require suitable planning, competent people and precautions against falls. The equipment and method must suit the task and its risks. Ladders are not banned, but they are not suitable for every job.
A customer’s instruction to “just get it done” does not remove safety duties. Permission to enter neighbouring land or use a neighbour’s roof is also a separate issue.
FICTIONAL TRADES EXAMPLE
Fictional example: A roofing contractor uses an unstable ladder for work that needs a safer access method. Finishing without anyone falling does not prove the method complied with the law. Safety rules address the risk of injury, not only accidents that actually happen.
COMPLIANCE TOPIC 06
Asbestos and hazardous materials
Older buildings can contain asbestos in insulation, boards and other materials. Disturbing it can release harmful fibres. The Control of Asbestos Regulations 2012 require suitable assessment, information, training and controls. Some work requires a licensed contractor.
The legal duty to manage asbestos applies to non-domestic premises and common parts of multi-occupancy homes. Common parts include shared stairs and corridors. An owner-occupied private home is treated differently, but contractors still have duties when working with possible asbestos.
Do not assume a material is safe because no asbestos register was provided. If suspect material is found, stop the activity that might disturb it and arrange a suitable assessment before continuing. The safe method and any licensing requirement depend on the material and the work.
FICTIONAL TRADES EXAMPLE
Fictional example: A plumber finds old insulation around pipes in the shared basement of a block of flats. The absence of paperwork does not justify cutting it away. The material and the planned work need to be assessed so the correct training, controls and any licensed contractor can be arranged.
COMPLIANCE TOPIC 07
Construction waste and environmental responsibilities
A waste carrier transports waste as part of a business. A waste broker arranges for other people’s waste to be transported or dealt with. These activities can require registration. The registration concerns the person or business, not a separate licence for each van.
Waste must go through a lawful disposal route, with the required records. Carrying your own building waste does not automatically exempt the business from registration. Construction and demolition waste can require upper-tier registration, including when the business produced it.
Check the correct registration category with the Environment Agency if based in England, or Natural Resources Wales if based in Wales. Keep records showing what was removed, who took it and where it went.
Check England’s waste-carrier register; waste-carrier registration in Wales.
FICTIONAL TRADES EXAMPLE
Fictional example: A builder’s price includes removing rubble and old bathroom fittings. That does not remove the waste-law duties. The builder should use the correct registration and lawful disposal route, and retain the required records. A customer asking for rubbish to be removed does not authorise fly-tipping.
COMPLIANCE TOPIC 08
Neighbours, boundaries and Party Wall rights
A party wall is commonly a wall shared by adjoining properties. The Party Wall etc. Act 1996 also covers certain boundary walls and nearby excavation. Some work requires the building owner to give formal notice before starting.
The Act can provide a process for resolving disagreements, protecting neighbouring property and compensating for damage. Planning permission does not replace that process.
Access is a separate question. The Act contains limited access rights subject to conditions; it is not a general right to enter a neighbour’s garden or put scaffolding on their roof. Check whether consent or a statutory procedure is needed.
Official explanation of party-wall notices, disputes and access.
FICTIONAL TRADES EXAMPLE
Fictional example: An extension requires cutting into a shared wall and placing scaffolding on a neighbour’s land. The owner and contractor should establish the required notices and the legal basis for access before work starts. The customer’s ownership of their own house does not give them unlimited control over the neighbouring property.
COMPLIANCE TOPIC 09
Insurance and promises to cover another person’s loss
Public liability insurance can cover certain claims for injury or damage to other people’s property. It is often required by a contract, but it is not legally compulsory for every trade.
Employers’ liability insurance covers certain claims by employees and is required for many employers, subject to exceptions. Professional indemnity insurance can cover claims about professional services or advice. The cover depends on the policy.
An indemnity in a contract is a promise to meet a specified loss or liability; it is not itself an insurance policy. Read the wording.
Insurance and legal responsibility are different questions. An insurer refusing cover does not automatically mean the contractor is not liable. An insurer accepting a claim does not replace the court’s role in deciding a disputed legal claim.
FICTIONAL TRADES EXAMPLE
Fictional example: A customer claims for water damage after plumbing work. The insurer says a policy exclusion applies. The customer still needs to establish who caused the damage and the amount legally recoverable. The insurance decision concerns cover; it does not, by itself, answer whether the plumber owes compensation.
COMPLIANCE TOPIC 10
Building safety and higher-risk buildings
Certain buildings have additional safety and building-control rules because of their height, use and other features. The legal category is called a higher-risk building. Do not decide that category from height alone.
In England, the Building Safety Regulator handles building-control approval for buildings within the relevant higher-risk category. Some work needs approval before it starts, together with evidence that the design, construction and management meet the rules.
In Wales, local authorities oversee building-control approval for higher-risk buildings. The Welsh definition and procedures differ. The English regulator’s process should not simply be applied to a Welsh project.
There can also be separate fire-safety and occupied-building duties. Identify the country, building, work and responsible people before deciding which approval or safety rule applies.
Higher-risk building approval in England; higher-risk building approval in Wales.
FICTIONAL TRADES EXAMPLE
Fictional example: A contractor is asked to carry out fire-safety repairs in a tall block of flats. Before quoting or starting, they check whether the building and work fall within the higher-risk rules. For work covered by the Welsh higher-risk regime, the building-control authority is the local authority, not England’s Building Safety Regulator. An ordinary house-repair process may be unsuitable.
These rules are wider than an unpaid-invoice dispute. A safety or approval failure may lead to regulatory action; a claim for money still needs its own legal basis and evidence. Use the linked legislation and current official guidance for the work and country involved.
For examples of how courts have applied related duties, see building-defect and safety cases. This section concerns England and Wales; requirements differ by trade, project and location.
BEFORE COURT
Before You Start a Court Claim
Before starting a court claim, check who made the agreement, what went wrong and what outcome you want. Work out the amount, keep the evidence and give the other side a fair chance to respond.
The steps required before court are called pre-action steps. The right steps depend on the people involved and the type of dispute.
PRE-ACTION STEP 01
Who should you bring the claim against?
The claimant starts the claim. The defendant is the person or business the claim is against. Start by checking who actually made the agreement.
A limited company is normally separate from its directors. A sole trader is an individual running a business, even if they use a business name. A letting agent and a landlord are also different parties.
Fictional example: A quotation names ABC Repairs Ltd and the company accepts it. The director later stops answering calls. That does not, by itself, make the director personally responsible for the company’s bill.
Check the quotation, work order, messages and payment records. Where an agent placed the order, check whom it was acting for and whether it had permission. Naming the wrong defendant can make an otherwise valid claim fail.
PRACTICAL CHECKS
PRE-ACTION STEP 02
What is the deadline for starting a claim?
Limitation means the legal time limit for starting a claim. For an ordinary contract claim in England and Wales, the usual limit is six years from when the right to sue arose. For an unpaid bill, this often means when payment became due and was not made.
Fictional example: An invoice is sent before the work finishes, but the agreement says payment is due after completion. The invoice date alone does not tell you when the six-year period starts.
Different claims and special circumstances can have different rules. Sending a demand letter or discussing settlement does not, by itself, stop time running. If a deadline may be close, get advice promptly.
PRACTICAL CHECKS
PRE-ACTION STEP 03
How much can you claim, and why?
Show how you reached the amount claimed. Start with the agreed price, add any properly agreed extra work, then subtract payments and credits. List any disputed deduction or other loss separately and explain it.
Fictional example: A decorating job costs £2,400 and the customer pays a £600 deposit. The starting unpaid balance is £2,400 − £600 = £1,800. If the customer says one room was unfinished, explain that dispute rather than treating the invoice as the whole answer.
Only add interest, recovery charges or other fees where the law or agreement allows them. The special charges for late business payments do not automatically apply to a private homeowner.
PRACTICAL CHECKS
PRE-ACTION STEP 04
Keep the evidence before it disappears
Evidence is the material used to establish what happened. Keep the original quote, work order, invoices, messages, photographs, videos, delivery notes and bank records.
Make a short timeline: date, event and the document that supports it. This helps the other side and the judge follow the story.
Fictional example: Keep the full message conversation showing that a customer approved an extra radiator and its price. One screenshot saying “go ahead” may leave out what was being approved.
Keep original files and complete conversations. Do not alter photographs or discard records because they are unhelpful to your case.
PRACTICAL CHECKS
PRE-ACTION STEP 05
Give the other side a fair chance to respond
Explain the problem in writing. Say what work was agreed, what happened, what is disputed and what you want done about it. Keep the tone calm and specific.
Fictional example: A customer says “the bathroom is wrong” and refuses to pay. Ask which items are defective, what correction is needed and how any deduction was calculated. Photographs and a repair quotation may help explain the complaint.
Where workmanship is disputed, consider a suitable inspection and an appropriate chance to put things right. Record requests, replies and offers. The right remedy depends on the agreement, the problem and any consumer rights that apply.
PRACTICAL CHECKS
PRE-ACTION STEP 06
Which rules apply before starting court proceedings?
A pre-action protocol is a set of steps for exchanging information and trying to resolve a dispute before court. Start by checking whether a particular protocol covers your claim.
- Construction and engineering disputes: these have their own protocol. Read its requirements and exceptions before choosing a process.
- A business seeking a debt from an individual: the Debt Claims Protocol generally applies, including where that individual is a sole trader, unless another protocol covers the claim. It requires particular information and documents. Where there is no reply, the normal minimum wait is 30 days after the Letter of Claim. A reply or request for documents can affect the next steps and timing.
- No specific protocol: the general pre-action guidance calls for a reasonable exchange of information and time to respond.
Do not choose a deadline only because the customer is a homeowner or a business. First identify the type of claim and the rules that cover it.
Construction and Engineering Disputes Protocol
Debt Claims Protocol · Practice Direction on Pre-Action Conduct · Debt Claims Protocol amendment effective 1 October 2026
Where the Debt Claims Protocol applies, check its current delivery requirements. The October 2026 amendment says a creditor who has the debtor’s personal email address should also send the Letter of Claim there. If no personal email is known but another personal electronic contact is known, use at least one such method as well. This supplements the protocol’s postal requirements.
PRACTICAL CHECKS
PRE-ACTION STEP 07
What should a Letter Before Action say?
A Letter Before Action, also called a Letter of Claim, explains your case before you start court proceedings. Sending it does not mean a court claim has begun.
The letter should identify both parties, describe the agreement or legal duty, explain what went wrong and state the outcome sought. Show the calculation and provide the information and documents required by the relevant pre-action rules.
Fictional example: For an unpaid decorating balance, explain the £2,400 agreed price, the £600 already paid and why you say the remaining £1,800 is due. Address any complaint about unfinished work.
Give the correct time to respond and say that court proceedings may follow. There is no single 14-day deadline for every letter. The relevant protocol may require a longer period and additional documents.
PRACTICAL CHECKS
PRE-ACTION STEP 08
Is going to court really the next step?
You may be able to agree payment or another solution without a court decision. This is called alternative dispute resolution, or ADR. It includes direct discussions and mediation, where an independent person helps both sides discuss an agreement.
Fictional example: A customer offers £1,500 to settle a £1,800 dispute. Before accepting, record whether that amount settles the whole claim, including any interest or fees, and when it must be paid. Do not leave the meaning of the offer unclear.
If court is still needed, check the defendant’s details, time limit, evidence, fees and pre-action steps. Also consider whether the defendant has money or assets. Winning a claim does not guarantee payment.
PRACTICAL CHECKS
The steps before court depend on the parties and the type of claim. This guide gives general information for England and Wales. It does not decide what should be done in an individual case.
EVIDENCE & PROOF
What Evidence Do You Need for a Small Claim?
In an ordinary civil dispute, the judge usually asks: is this fact more likely to be true than not? This is called the balance of probabilities. A person relying on a disputed fact normally has to prove it.
Evidence helps answer that question. A short timeline and relevant records can explain your case more clearly than a large folder with no explanation of what each item shows.
EVIDENCE TYPE 01
Agreements and the work included
The quotation, work order, terms and messages can show what work and price were agreed. A later agreed change is called a variation. An unsigned document can still matter if the parties acted on its terms.
Fictional example: A quote includes painting three rooms. A later message approves a fourth room for £300. Keep both documents: one shows the original job and the other helps show the agreed extra.
A document showing what was agreed does not, on its own, prove that the work was completed.
WHY THIS EVIDENCE MATTERS
EVIDENCE TYPE 02
Invoices, payments and materials
An invoice records what someone is asking to be paid. It does not, by itself, prove that the whole amount is owed. Use the agreement, payment records and other evidence to explain the figures.
Fictional example: A £2,400 job less a £600 deposit leaves a starting balance of £1,800. The quotation supports the price; the bank record supports the deposit. Any extra work, credit or disputed deduction needs its own explanation.
Keep receipts and supplier records where they help explain a cost. Show the calculation clearly, including the basis of any interest or fee.
WHY THIS EVIDENCE MATTERS
EVIDENCE TYPE 03
Emails, messages and instructions
Messages can show instructions, agreed prices, complaints and offers to return. Save the whole conversation, including dates, names and attachments.
Fictional example: “Go ahead” could approve a £300 extra, a free correction or an inspection. The earlier messages show which one was meant. An isolated screenshot may leave that important point unclear.
WHY THIS EVIDENCE MATTERS
EVIDENCE TYPE 04
Photographs and videos
Photographs and videos can show the condition of work or property. Keep the original files and note when, where and by whom they were taken.
Fictional example: A photograph shows a wet ceiling after a boiler repair. It helps establish the damage, but it does not necessarily show whether the boiler repair caused the leak. Earlier photographs, inspection findings and the timing of events may help answer that separate question.
WHY THIS EVIDENCE MATTERS
EVIDENCE TYPE 05
Witnesses and site records
A witness explains what they personally saw, heard or did. A witness statement is their written account for the court. It should identify the relevant events and documents, and use the required statement of truth when signed.
Fictional example: An installer can describe fitting a pipe and testing it. They should not claim to know what another contractor did afterwards unless they witnessed it or clearly identify the source of that information.
Job sheets, diaries and attendance records can help the witness give dates and explain the order of events.
WHY THIS EVIDENCE MATTERS
EVIDENCE TYPE 06
Technical reports and expert evidence
An expert uses specialist knowledge to give an opinion, such as why a heating system failed. This is different from a witness describing something they personally saw.
Court permission is required for expert evidence, written or spoken, at a small-claims hearing. Check the court’s instructions before arranging a report for that purpose.
Fictional example: A £900 repair quotation may help show the proposed cost of putting work right. It does not automatically prove who caused the fault, and it is not automatically an independent expert report.
WHY THIS EVIDENCE MATTERS
How a Judge Decides What the Evidence Shows
The judge considers whether the disputed facts are more likely to be true than not. They look at the reliability, consistency and context of the evidence.
Fictional example: Twenty payment reminders show that a bill was chased. They do not necessarily prove that an extra £500 was agreed. A complete message conversation approving that extra may be more useful on that particular issue.
Small-claims hearings use simpler procedures, but court instructions still matter. Standard directions usually require the documents you will rely on to reach the court and the other side at least 14 days before the hearing. Follow your court order if it sets a different requirement. Expert evidence at the hearing needs court permission.
Quick help with court stages
Use these short explanations when you receive a court notice. The detailed process guide follows below. Always follow the dates and instructions for your own case.
Directions Questionnaire: what it is for
A Directions Questionnaire gives the court information needed to manage a defended claim, such as witnesses, availability and hearing arrangements. Form N180 is commonly used for proposed small claims, but an online claim may ask for the information online. Check which form or task the court has actually sent, the deadline, and who must receive a copy. It is not a witness statement or a substitute for a Defence.
Follow the questionnaire step in Making a Small Claim or Defending a Small Claim, and use the official N180 form and guidance.
Small claims mediation
For a disputed money claim of £10,000 or less, the court will normally require free mediation. Check the notice for your case. The appointment is usually by telephone and can last up to an hour. The mediator helps the parties explore agreement and does not decide the case. Prepare your figures, the points you need to resolve and any terms you could accept. A settlement can be binding; missing a required appointment can lead to sanctions.
Read the current GOV.UK mediation guidance.
Court directions and evidence deadlines
Directions are the court’s instructions for preparing the case. Make a checklist of every task, deadline and recipient. “File” means send to the court; “serve” means send to another party. The standard small-claims directions usually require copies of the documents relied on at least 14 days before the hearing, but your court order may specify a different timetable. Keep proof of sending, and raise any difficulty promptly rather than missing the date silently.
Use the evidence and proof section and check CPR Part 27. Expert evidence needs the court’s permission.
Quick questions about building and repair claims
Is every claim under £10,000 a small claim? No. Value matters, but the court also considers the type and complexity of the case, and some claims have different limits.
Is a Letter Before Action a court claim? No. It is a pre-action demand. An issued claim comes with court information and a response deadline that must be dealt with separately.
Can I present my own case? Yes. Many people do, but they must still meet deadlines and prove their position with relevant evidence.
Does TDD cover every dispute described here? No. The law guide is general information. TDD’s standard fixed-price claim and defence services are for eligible contractual money disputes; negligence-only claims are excluded. Technical support is assessed and quoted separately. Check the service terms and the relevant service page.
RUNNING A SMALL CLAIM
Small Claims: From Starting a Claim to the Court’s Decision
The small claims track is a simpler procedure within the County Court. It is commonly used for straightforward money disputes. The steps below explain starting a claim, responding to it and what happens after the judge’s decision. Follow the dates and instructions in your own court papers.
SMALL CLAIMS STAGE 01
Starting the claim
To start a claim, identify the correct claimant and defendant, explain the claim and state the amount or other outcome sought. Pay the court fee, unless help with the fee applies.
Particulars of Claim means the explanation of your case: what agreement or duty you rely on, what went wrong and how you worked out the amount.
Fictional example: For a £1,800 decorating balance, explain the £2,400 agreement, the £600 payment and why you say the work was completed and the balance is due. The invoice alone does not answer every possible dispute.
Many money claims can be started online; others need paper Form N1 or another route. Check the official instructions and complete the relevant pre-action steps first.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 02
The defendant’s response
The defendant may pay, admit all or part of the claim, dispute it, or take another response step allowed by the court process. Read the claim papers immediately and use the stated response route.
Service means formally delivering court documents in the way the rules allow. In an ordinary Part 7 claim, the usual defence deadline is 14 days after service of the Particulars of Claim. An acknowledgment of service filed on time can extend this to 28 days from that service date. This acknowledgment tells the court the claim has been received; it is not the defence itself.
Online procedures and other situations can have different arrangements. Follow the notice for your claim. If the defendant does not respond, the claimant may be able to request default judgment: a decision without a contested hearing. The conditions must be met; it is not an automatic win when the deadline passes.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 03
Answering a claim and bringing a claim back
A Defence is the defendant’s formal explanation of why all or part of the claim is disputed. Answer the specific allegations. State what is accepted, what is denied and why, and what cannot be confirmed.
Fictional example: A customer claims £1,500 for floor damage after a carpenter’s visit. The carpenter accepts working in the room but says the damage was already present. A useful response explains that position and identifies the dated photographs. Saying only “I owe nothing” leaves the reason unclear.
A counterclaim is a separate claim made by the defendant against the claimant. It needs its own facts, legal basis and calculation, and can require a court fee. A complaint or deduction is not automatically a valid counterclaim.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 04
The questionnaire and the court’s choice of process
A Directions Questionnaire asks for practical details such as witnesses, unavailable dates and hearing needs. The court may use Form N180 or online questions.
The court then chooses a procedure, called a track. This choice is called allocation. Most straightforward money claims worth no more than £10,000 normally use the small claims track, but there are exceptions. The court also considers the type and complexity of the case.
Fictional example: If you will give evidence yourself, include yourself when answering the question about witnesses. Do not count someone merely because they have helped organise your papers.
Return the questionnaire as instructed and read the court’s next order carefully.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 05
Mediation and settlement
Mediation is a discussion with an independent person who helps both sides try to agree a solution. The mediator does not decide who is right. Court-organised small-claims mediation is free and usually uses separate telephone conversations, in an appointment lasting up to an hour.
For many disputed money claims of £10,000 or less, attendance is required. Follow your notice and take part properly. Missing a compulsory appointment can lead to consequences such as a costs order.
You decide whether to accept a settlement. An agreement reached at the appointment is legally binding, so check the amount, payment dates and what it settles before agreeing. If no agreement is reached, the claim continues through the court process.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 06
The court’s instructions and your evidence
Directions are the court’s instructions about what to do and by when. They tell you which documents to provide and whether witness statements are required.
- File: send the document to the court in the required way.
- Serve: give it to the other party in the required way.
- Witness statement: a witness’s written account of relevant events.
- Bundle: the organised collection of documents required for the hearing.
Standard small-claims directions usually require documents at least 14 days before the hearing, but your court order may set different requirements. Record each deadline and keep proof of sending.
Use the quote, messages, photographs and payment records to support particular points. Court permission is required for expert evidence at the hearing.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 07
Hearing, judgment and costs
At the hearing, the judge considers the disputed facts, the evidence and the law. A small-claims hearing is usually less formal than a larger trial, but both sides must follow the judge’s instructions.
Be ready to explain what was agreed, what happened and how the amount was calculated. When referring to a document, help the judge find the relevant page.
A judgment is the court’s decision. It may include an order to pay money. The judge will explain the reasons.
The winning side cannot normally recover all its legal fees on the small claims track. Court fees and some allowed expenses may be recoverable. Unreasonable conduct can lead to additional costs. Check exactly what the order requires.
PRACTICAL CHECKS AT THIS STAGE
SMALL CLAIMS STAGE 08
Payment and Collecting an Unpaid Judgment
If a judgment orders payment, read the amount and payment deadline carefully. The debtor owes the money; the creditor is entitled to receive it.
If payment is not made, enforcement means asking the court to take a further step to recover it. Depending on the debtor’s circumstances, options may include:
- A warrant of control: asking bailiffs to collect payment or take eligible goods for sale.
- An attachment of earnings order: arranging deductions from an employed individual’s wages.
- A third-party debt order: seeking money held for the debtor, for example in a bank account.
- A charging order: securing the debt against certain assets, such as a property. This does not itself produce immediate payment.
Each route has conditions and may involve another application and fee. Check which fits the debtor’s income or assets. A judgment does not create money where none is available.
PRACTICAL CHECKS AT THIS STAGE
Throughout your case: keep the claim number and court notices, record every deadline, send documents as instructed and consider reasonable ways to settle.
Making a money claim · mediation · CPR Part 27 · case law about court procedure · practical small-claims scenarios
TRADES DISPUTE EXAMPLES
How the Law Applies to Everyday Trades Disputes
These sixteen fictional examples show how legal rules can affect real kinds of trades dispute. Each explains the facts that matter, the reason they matter and useful evidence.
They are teaching examples, not customer case studies or promises about how a court will decide your case. Different facts or contract terms can change the result.
Find an Example by Legal Issue
Agreements, Extra Work and Consumer Rights · Agents and Subcontractors · Careless Work, Damage and Safety · Payments, Money Held Back and Business Risk · Before Court and the Small Claims Process
Agreements, Extra Work and Consumer Rights
These examples explain agreed prices, extra work, defects and consumer rights. Related court decisions cover making a contract, defective work and rights given by legislation.
Agency and Subcontractors
These examples explain permission to order work and why missing a construction-payment notice can change what must be paid now. Related court decisions cover agents and construction contracts.
Negligence, Damage and Building Safety
Who caused the damage, which safety rules apply and what the evidence shows. These are separate questions, even when they arise on the same job.
Payment, Money Held Back and Business Risk
When a final bill is due, what can be added to a late business payment, and what happens if the customer’s company cannot pay.
Before Court and the Small Claims Process
Naming the correct person or company, following the steps before court and meeting court deadlines.
What These Examples Have in Common
For every dispute, ask four questions: What was agreed or required by law? What went wrong? What proves it? What result does the law allow?
Show your calculation if you are asking for money. Explain the disputed facts if you are answering a claim. Strong feelings alone cannot prove either side’s case.
Before Court · Evidence & Proof · Running a Small Claim · Case Law & Precedent
REAL COURT DECISIONS AND THE RULES THEY EXPLAIN
Trades Dispute Case Law: Real Court Judgments
A judgment is a court’s decision and its reasons. These real cases explain how judges apply legal rules to particular facts. They can help you understand an argument, but they cannot predict the result of your own dispute.
How Can an Earlier Case Affect Yours?
Courts use both legislation—laws passed by Parliament—and rules developed in earlier court decisions.
A legal rule established by a higher court may have to be followed by a lower court. This is called binding precedent. The rule must be relevant to the later dispute.
The key rule needed to decide the earlier case is sometimes called the ratio decidendi. You do not need to use that Latin phrase. Ask: “What legal reason led the court to this result, and does that reason fit my facts?”
Why an Earlier Win Doesn’t Guarantee Yours
Two cases can look similar but turn on different facts. For example, a few repairable defects are different from a heating system that fails to heat the house properly.
A judge may explain why an earlier case does not decide the new dispute. Lawyers call this distinguishing the earlier case. Later laws or decisions can also change how an older case applies.
Most decisions below concern civil disputes. R v Chargot is a criminal health-and-safety case and is labelled separately. It explains a safety duty, not who wins an ordinary unpaid-invoice claim.
18 Real Judgments, Organised by Legal Topic
Choose a topic and open a case. Each summary explains what happened, what the court decided and why the point matters in a trades dispute.
Making and changing agreements · Faulty work and compensation · Agents and who must pay · Subcontractors and payment rules · Damage and safety · Consumer and worker rights · Court procedure
Making Agreements, Changing Terms and Extra Payment
How an agreement becomes binding, how its terms can change and when a promise of extra payment can be enforced.
Faulty Work, Compensation and Promised Specifications
Why the seriousness of a defect matters, how compensation is assessed and why the promised specification must be checked.
Agents and Who Agreed to Pay
Why the person placing an order and the person legally responsible for paying may be different.
Subcontractors, Payment Notices and Quick Dispute Decisions
Rules about construction payments, quick decisions by adjudicators, promises to building users and companies that cannot pay.
Damage Claims and Building-Safety Duties
Who can be responsible for unsafe building work, and why workplace-safety duties apply separately from payment disputes.
Consumer Terms and Rights at Work
How the real working arrangement and consumer-protection rules can affect rights, despite the labels or charges in a contract.
Trying to Settle and Following Court Rules
Why courts can require attempts to settle, and why people without solicitors still need to follow court instructions.
These summaries explain selected points from real judgments. They are general information, not advice on an individual dispute. Read the full decision and check relevant laws and later cases before relying on it. The facts and wording of your own agreement can change the answer.