THINGS THAT MAKE YOU LOOK SMART

Case law for tradespeople: 20 stories worth knowing

Old cases. Familiar problems. A little legal knowledge for the next time someone says, “That’s not my responsibility.”

Agency, contracts, payment and negligence—explained through the jobs engineers and tradespeople do today. Pick a story while the kettle boils.

General education for England and Wales, not advice on an individual dispute. The trade examples are illustrations. The tea-break lines are our own summaries, not quotations from the judges.

Published by Tradesmen Dispute Direct · Sources checked 25 November 2026

First: why does a very old case still matter?

Case law is law explained and developed through court decisions. Precedent means that a legal rule necessary to a higher court’s decision can bind lower courts in later cases where it applies. That necessary reasoning is the ratio decidendi. Other observations, called obiter dicta, may be persuasive without being binding.

A judge can distinguish a case because important facts differ. Later decisions and legislation can also change the rule. A small-claims result in somebody else’s county-court case is not automatically binding precedent.

These are useful landmark cases, rather than a claim that each one invented its whole subject. Some are centuries old; others show how the rule developed. A case name is a starting point for understanding an issue, not a substitute for proving what happened on your job.

Responsibility beyond the customer

First, the famous bottle—and why your responsibilities can reach beyond the person paying you.

1. You can owe a duty to someone who never hired you

Donoghue v Stevenson · [1932] AC 562 · House of Lords

The story. In 1928, May Donoghue drank ginger beer bought by a friend. She alleged that the opaque bottle contained a decomposed snail. She had no contract with the manufacturer. The House of Lords held that her negligence claim could proceed; it did not decide at that stage that the snail story had been proved.

The principle. A duty of care can exist without a contract. The case helped establish the modern neighbour principle: think about people closely and foreseeably affected by what you do.

On site today. A roofer negligently secures a tile. It falls onto the neighbour’s car. The neighbour did not order the roof, but may still have a negligence claim. They must prove the relevant duty, breach and resulting damage; a falling tile does not automatically settle all of that.

Your line at the tea break
“You don’t need to be my customer for me to owe you a duty of care. That’s the snail-in-the-bottle case.”

2. You need not predict the exact way an accident happens

Hughes v Lord Advocate · [1963] AC 837 · House of Lords

The story. Post Office workers left a manhole and paraffin warning lamps unattended. Children explored the site. A lamp fell into the hole, an unusual explosion followed and a boy suffered serious burns. The precise explosion had not been expected, but burns were a foreseeable kind of injury.

The principle. For negligence, the general kind of harm can be foreseeable even when the detailed chain of events is surprising.

On site today. Leaving hot equipment or an exposed work area accessible to children is not made safe by saying, “I never thought they would do that.” Assess the foreseeable hazard and who might encounter it. This does not make every unusual accident your responsibility.

Your line at the tea break
“You don’t have to predict the whole accident, just the kind of harm you’ve created a risk of.”

Who are you dealing with—and who can say yes?

A name on a van, a person with keys and an authorised customer are not necessarily the same thing.

3. John the builder and John’s limited company are different people

Salomon v A Salomon & Co Ltd · [1897] AC 22 · decided 1896 · House of Lords

The story. Aron Salomon transferred his boot-making business to a company largely owned by him and his family. When it failed, an attempt was made to make him answer for its debts. The House of Lords recognised the company as a separate legal person.

The principle. A properly incorporated company has its own rights and debts. Owning or running it does not, by itself, make someone personally responsible for its contracts.

On site today. Check whether the quote is from “John Smith” as a sole trader or “Smith Roofing Ltd”. The person you chat to may not be the person who owes the invoice or promises the work. Personal guarantees, someone’s own wrongdoing and statutory liabilities can change the position.

Your line at the tea break
“The logo isn’t the legal person. Who actually signed up for the job?”

4. Authority can come from what someone is allowed to do

Hely-Hutchinson v Brayhead Ltd · [1968] 1 QB 549 · decided 1967 · Court of Appeal

The story. A company chairman regularly acted as its chief executive, making decisions which the board accepted. He gave financial commitments without specific express permission. The court found actual authority could be implied from the way the business had allowed him to operate.

The principle. Actual authority may be express or implied. An express instruction is one route; the principal’s conduct and the established working arrangement can be another.

On site today. A landlord regularly lets a managing agent arrange routine repairs and approves that pattern. The agent may have implied authority for work within that role. That does not automatically extend to a major refurbishment or work outside known spending limits.

Your line at the tea break
“There’s express authority, and there’s authority implied by how they actually run the place.”

5. Someone may look authorised because the customer made them look that way

Freeman & Lockyer v Buckhurst Park Properties (Mangal) Ltd · [1964] 2 QB 480 · Court of Appeal

The story. A director instructed architects for a property company although he had never been formally appointed managing director. The board had allowed him to act in that position. The company was bound by the authority it had represented him as having.

The principle. Apparent, or ostensible, authority concerns what the principal has represented to the other contracting party. The contractor must have relied on that representation; the supposed agent cannot simply invent their own authority.

On site today. An owner introduces someone as the person handling the job and lets them approve comparable work. That may support apparent authority. Merely arriving on site with keys, a clipboard or a very confident voice does not prove permission to order extras.

Your line at the tea break
“A clipboard isn’t authority. What did the customer do to make you think they could approve it?”

6. “I’m authorised” can be a promise of its own

Collen v Wright · (1857) 8 E & B 647 · Exchequer Chamber

The story. A land agent agreed a farm lease for an owner but lacked the authority he claimed to have. He believed he was authorised. His estate was nevertheless liable for loss caused by that false assurance of authority.

The principle. Someone purporting to act as an agent can give an implied warranty that they have the authority they claim. An honest mistake does not necessarily avoid liability.

On site today. A property manager orders a replacement system saying the landlord has approved it. If there is no actual or apparent authority binding the landlord, a claim against the manager for breach of warranty of authority may need examining. It is not an automatic right to collect the entire invoice from them.

Your line at the tea break
“If you promise you’re authorised, that promise can have consequences too.”

Was there a contract, and what did it include?

Silence, signatures, small print and the surprisingly expensive words “just do that while you’re here”.

7. No reply is not the same as yes

Felthouse v Bindley · (1862) 11 CB (NS) 869 · Court of Common Pleas

The story. An uncle wanted to buy his nephew’s horse and wrote that, if he heard no more, he would consider it his. The nephew intended to sell to him, but did not communicate acceptance. The uncle could not turn silence into a completed sale.

The principle. An offeror cannot normally impose acceptance by saying that a failure to reply will count as agreement.

On site today. “I’ll add £600 unless you object by Friday” is weak evidence of an agreed extra if the customer never responds. Get positive approval. Later conduct may show agreement, but that is a different question from silence alone.

Your line at the tea break
“A blue tick is not a purchase order.”

8. An unsigned document does not always mean no contract

Brogden v Metropolitan Railway Co · (1877) 2 App Cas 666 · House of Lords

The story. A coal supplier returned an amended draft agreement. The railway filed it without completing the formal paperwork, but the parties then ordered and supplied coal on its terms. Their conduct showed a contract.

The principle. Agreement can be demonstrated by conduct, not just a signature. The modern Supreme Court applied the objective approach to unsigned arrangements in RTS Flexible Systems v Müller (2010).

On site today. A customer accepts the agreed scope in practice: grants access, instructs the work and pays agreed stages. Those actions can help establish a contract. They do not automatically prove every term on an unsigned quote. Genuine “subject to contract” wording and formal requirements need separate attention.

Your line at the tea break
“The contract might be in what you both did, even if the signature box is empty.”

9. “I didn’t read it” is usually a poor plan

L’Estrange v F Graucob Ltd · [1934] 2 KB 394 · Divisional Court

The story. A café owner signed an agreement to buy a cigarette machine without reading the small print. The machine disappointed, but the court treated her as bound by the contractual terms she had signed.

The principle. Signing a contractual document generally binds you to its terms, even if you did not read them. Fraud, misrepresentation and other exceptions matter.

On site today. Read the subcontract before signing it, especially the scope, payment dates, design promises and change procedure. A signature is not a magic stamp making every clause lawful: consumer protections and controls on exclusions and unfair terms still apply.

Your line at the tea break
“Signing it and reading it are separate jobs. The law tends to assume you did both.”

10. Terms on the final invoice may arrive too late

Thornton v Shoe Lane Parking Ltd · [1971] 2 QB 163 · decided 1970 · Court of Appeal

The story. A driver entered an automatic car park and received a ticket referring to conditions. The operator tried to rely on a liability exclusion. The contract had already been made at the machine, and adequate notice of the exclusion had not been given.

The principle. Terms normally need to be brought into the bargain before or when it is made. Particularly onerous terms require particularly clear notice.

On site today. An unexpected cancellation charge or liability exclusion first printed on the invoice does not automatically become part of the earlier agreement. Send terms with the quote and draw attention to unusual provisions. Even properly included terms remain subject to statutory controls.

Your line at the tea break
“You can’t usually add the small print after we’ve done the handshake.”

11. The contract may specify how extras must be agreed

Rock Advertising Ltd v MWB Business Exchange Centres Ltd · [2018] UKSC 24 · Supreme Court

The story. An office occupier relied on an oral agreement to rearrange payments. Its written contract required variations to be written and signed. The Supreme Court upheld that requirement.

The principle. A clause requiring written, signed changes can be effective. “We agreed it on the phone” may not satisfy the agreed procedure. Estoppel can sometimes prevent injustice, but requires more than the informal promise itself.

On site today. Check the variation clause before moving the boiler, adding sockets or agreeing another payment date. Record the changed scope, price and timing through the required process, with someone authorised to agree it. A casual WhatsApp message may not meet every contractual formality.

Your line at the tea break
“Before we agree the extra, how does this contract say we have to agree extras?”

Payment, pressure and the snagging list

When the argument moves from “lovely job” to “we need to discuss your invoice”.

12. A promise to pay more can buy a practical benefit

Williams v Roffey Bros & Nicholls (Contractors) Ltd · [1991] 1 QB 1 · decided 1989 · Court of Appeal

The story. A carpenter’s subcontract was priced too low and he struggled to finish. The main contractor promised extra payment to keep the project moving and avoid delay consequences. The practical benefit could support that promise even though the carpenter already owed the work.

The principle. In this setting, a practical benefit can provide consideration—the legal exchange supporting a promise—to pay more. The court expressly excluded fraud and economic duress.

On site today. A properly negotiated rescue agreement may be enforceable. This is not permission to underquote, threaten to walk off and demand more. Record the genuine new bargain and comply with any variation clause. Agreements to accept less of an existing debt raise different rules.

Your line at the tea break
“Keeping the job on programme can be a practical benefit. Holding it hostage is another matter.”

13. “Take less or get nothing” is not always a binding settlement

D & C Builders Ltd v Rees · [1966] 2 QB 617 · decided 1965 · Court of Appeal

The story. A small building company was owed £482. Knowing it was in financial trouble, the customer’s wife pressed it to accept £300 in full settlement. The builders accepted under pressure but were allowed to pursue the balance.

The principle. Part-payment does not automatically discharge the rest of an admitted debt. The circumstances of the bargain, consideration and equitable principles matter; this was not treated as a genuine voluntary settlement.

On site today. Writing “full and final” on a transfer does not unilaterally wipe an invoice. Equally, a genuine compromise of a disputed claim can bind you. Do not assume you can accept settlement money and always sue for the rest.

Your line at the tea break
“‘Full and final’ isn’t a spell you cast from the banking app.”

14. A snag is not always a free job

Hoenig v Isaacs · [1952] 2 All ER 176 · Court of Appeal

The story. An interior decorator substantially completed a flat’s decoration and furnishing, but there were defects. The customer could not refuse the entire price; the contractor recovered it less the amount needed to put the defects right.

The principle. Substantial performance of a lump-sum contract can allow recovery of the price with an appropriate deduction for defects. The actual contract and the seriousness of the shortfall matter.

On site today. A small, repairable decorating defect may justify a proportionate deduction rather than withholding every penny. The contractor still has to address the problem. Retentions, payment clauses and consumer remedies may produce different questions.

Your line at the tea break
“A snagging list is not automatically a voucher for a free refurbishment.”

15. But an installation that fails at its main job is different

Bolton v Mahadeva · [1972] 1 WLR 1009 · Court of Appeal

The story. A central-heating installation gave off fumes and did not adequately heat the house. Putting the defects right required significant work. Unlike the relatively limited defects in Hoenig, the contract had not been substantially performed, so the main contract price was not recoverable in that action.

The principle. Substantial performance is about the nature of the defects as well as their cost. There is no universal “under ten per cent is fine” rule.

On site today. A boiler system that is unsafe or cannot heat the agreed rooms is not just a few cosmetic snags. Investigate the technical evidence and the contract before asserting either “pay everything” or “pay nothing”. Modern consumer rights also apply.

Your line at the tea break
“If the heating doesn’t heat, calling it snagging won’t warm the house.”

What did the mistake actually cost?

A breach is the start of the damages question. It does not settle every pound on the claim.

16. You do not automatically pay every knock-on loss

Hadley v Baxendale · (1854) 9 Ex 341 · Court of Exchequer

The story. A carrier delayed a broken mill shaft being sent away to make a replacement. The mill owners claimed lost profits. The carrier had not been given the relevant special circumstances explaining why that delay would cause those losses.

The principle. Contract damages generally cover losses arising ordinarily from the breach, or losses within both parties’ reasonable contemplation because special circumstances were communicated when contracting.

On site today. A late repair at a café may lead to a claimed loss of trading income. Ask what the contractor knew at the start, whether the breach caused the loss and how it is evidenced. A large number on a spreadsheet is not enough; nor is every lost-profit claim automatically too remote.

Your line at the tea break
“Did you tell me the whole business depended on that part when we made the deal?”

17. Putting it right must be a reasonable way to compensate the loss

Ruxley Electronics & Construction Ltd v Forsyth · [1996] AC 344 · decided 1995 · House of Lords

The story. A swimming pool was shallower than the contract specified, but safe and usable, with no reduction in value. Demolishing and rebuilding it would have cost £21,560. The court rejected that disproportionate cost and restored a £2,500 award for lost amenity.

The principle. A breach does not automatically justify the most expensive possible cure. Reasonableness, the contractual objective and the actual loss matter.

On site today. Replacing an entire otherwise serviceable installation over a limited departure from the specification may need justification. This is not a licence to ignore dimensions, appearance or customer preferences, and does not excuse unsafe work. A serious defect may justify extensive reinstatement.

Your line at the tea break
“There’s a breach. Now we need to ask what a reasonable remedy actually costs.”

18. You cannot let avoidable damage grow and invoice it all later

British Westinghouse v Underground Electric Railways · [1912] AC 673 · House of Lords

The story. Defective turbines were replaced with more efficient machines. The dispute required the court to consider both the loss and financial benefits arising from that reasonable response. Compensation had to reflect the resulting position.

The principle. A claimant must take reasonable steps to limit loss. Avoidable losses may be unrecoverable, and relevant benefits of mitigation may have to be accounted for. The law does not demand unreasonable sacrifices.

On site today. If a defective pipe is leaking, isolate the water where safe and arrange proportionate emergency protection. Photograph the problem and keep receipts. Letting water run to make the eventual claim bigger is a poor strategy. Emergency safety measures need not wait for a leisurely exchange of letters.

Your line at the tea break
“Mitigation: turn the water off before you start the argument.”

19. A delay charge needs more than a frightening number

Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd · [1915] AC 79 · decided 1914 · House of Lords

The story. A tyre dealer promised payments for breaking resale restrictions. The House of Lords upheld the provision and set out influential guidance distinguishing agreed damages from penalties.

The principle. The modern approach comes from Cavendish and ParkingEye v Beavis (2015): a secondary obligation triggered by breach must not impose a detriment out of all proportion to the innocent party’s legitimate interest. The old “genuine pre-estimate of loss” shorthand is not the whole current test.

On site today. A contract’s weekly delay charge may be enforceable, but a wildly excessive sanction can be challenged. Calling it “liquidated damages” does not decide that. Consumer fairness rules may also apply. Check the clause, the protected interest and the actual contractual trigger.

Your line at the tea break
“Writing ‘liquidated damages’ above it doesn’t make any number you fancy enforceable.”

20. Following a standard may not satisfy a stronger contractual promise

MT Højgaard A/S v E.ON · [2017] UKSC 59 · Supreme Court

The story. Wind-turbine foundations failed despite a design following an industry standard whose calculation contained an error. The contract also imposed a twenty-year design-life requirement. Following the standard did not remove that stronger obligation.

The principle. A contract can promise a result as well as reasonable skill and compliance with a technical standard. Read the agreement and its technical documents together.

On site today. Promising a waterproof system, a specified output or a particular design life may create obligations beyond “we followed the instructions”. Identify which promises you actually made and whether you controlled the design. This case does not impose a blanket twenty-year guarantee on every trade job.

Your line at the tea break
“‘Built to the standard’ and ‘delivered what we promised’ can be two different questions.”

The old cases are only part of the job

For work supplied to a consumer, modern legislation matters alongside case law. The Consumer Rights Act 2015 requires reasonable care and skill, provides remedies and limits attempts to exclude those service rights. Unfair-term controls and other rules can also affect what a contract can enforce.

Read the actual agreement, identify the correct parties and keep the messages, photographs and payment records. The best story in this list cannot replace missing evidence.